Week 34 progress report is for work completed up to the end of April. Works completed up to Week 34 included:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 100% topsoil stripping completed;

  • 100% earthworks cut and fill completed;

  • 100% sewer trenching, pipe installation and construction of sewer manholes completed;

  • 100% stormwater pipes layed and 100% stormwater pits installed;

  • 100% sewer pump station components completed;

  • 100% watermain works commenced and 80% of water services;

  • 100% subsurface drains completed;

  • 100% demolition of entry house and clearing works completed;

  • 80% electrical high voltage, 60% low voltage, 45% street lights completed;

  • Road subbase construction commenced;

  • Sewer rising main installation commenced;

  • Removal of rail infrastructure, stripping in rail corridor and construction of ‘at grade’ crossing commenced;

  • NBN installation commenced;

  • Kerb & gutter commenced.