Week 43 progress report is for work completed up to the end of June. Works completed up to Week 43 included:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 100% topsoil stripping completed;

  • 100% earthworks cut and fill completed;

  • 100% sewer trenching, pipe installation and construction of sewer manholes completed;

  • 100% stormwater pipes layed and 100% stormwater pits installed;

  • 100% sewer pump station components completed;

  • 100% watermain works commenced and 100% of water services with connection still to occur;

  • 100% subsurface drains completed;

  • 100% demolition of entry house and clearing works completed;

  • 90% of electrical works completed;

  • 90% of road subbase construction completed;

  • 90% of sewer rising main installation completed;

  • 90% of NBN installation completed;

  • 85% of kerb & gutter completed

  • 10% of footpaths completed

  • Re-topsoiling of lots and verge commenced.