Works to week 9 have seen good progression with two solid weeks of good weather that enabled approximately 64 percent of general earthworks to be completed. The site is taking shape with the hint of lot pads and roads starting to form up.

Works onsite have included:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 64% of earthworks cut and fill;

  • Material procurement;

  • Preparation for demolition of house on entry road;

  • Progressing sewer pump station construction certificate approval with Yass Valley Council.