Yarrah Stage 1 Construction Completion Update
Aside from minor maintenance and landscaping consolidation activities, the Principal Contractor has provided notification this week that as of the 24 February 2023 works are completed onsite.
Aside from minor maintenance and landscaping consolidation activities, the Principal Contractor has provided notification this week that as of the 24 February 2023 works are completed onsite.
Week 65 progress report is for work completed up to mid-December. Works completed up to Week 65 included: Monitoring of safety, environmental, erosion and quality controls; 100% topsoil
Week 58 progress report is for work completed up to the end of October. Works completed up to Week 58 included: Monitoring of safety, environmental, erosion
Week 49 progress report is for work completed up to the end of August. Works completed up to Week 49 included: Monitoring of safety, environmental, erosion
Week 43 progress report is for work completed up to the end of June. Works completed up to Week 43 included: Monitoring of safety, environmental, erosion
Week 34 progress report is for work completed up to the end of April. Works completed up to Week 34 included: Monitoring of safety, environmental, erosion
Week 25 progress report is for works up until the end of February. A new up-to-date progress report is expected soon. Works completed up to Week 25
Week 19 progress report covers the first two weeks of works after a two week site shut down due to the Christmas holiday break. As of
Week 15 brings civil works up to the Christmas holiday break. Prior to week 15, works were ahead of schedule, however, progress has been slowed by wet
Works to week 9 have seen good progression with two solid weeks of good weather that enabled approximately 64 percent of general earthworks to be completed. The