Yarrah Stage 1 Construction Update – Week 34
Week 34 progress report is for work completed up to the end of April. Works completed up to Week 34 included: Monitoring of safety, environmental, erosion
Week 34 progress report is for work completed up to the end of April. Works completed up to Week 34 included: Monitoring of safety, environmental, erosion
Week 25 progress report is for works up until the end of February. A new up-to-date progress report is expected soon. Works completed up to Week 25
Week 19 progress report covers the first two weeks of works after a two week site shut down due to the Christmas holiday break. As of
Week 15 brings civil works up to the Christmas holiday break. Prior to week 15, works were ahead of schedule, however, progress has been slowed by wet
Works to week 9 have seen good progression with two solid weeks of good weather that enabled approximately 64 percent of general earthworks to be completed. The
The past 7 weeks have been very busy onsite for Yarrah Stage 1 civil works with substantial rainfall experienced over September and October. Initial site works included
Stage 1 Civil Construction kicked-off at Yarrah, Yass in early September 2021. Civil works are being undertaken by Woden Contractors, who will delivery the entire stage including 62 residential lots,