A lot has been happening in stage 2A recently. Civil construction commenced in March 2024 and is expected to be completed by June 2024 with house construction expected to start in Spring 2024.

Stage 2A includes lots 67 to 75 along Yarrah Drive and Wood street, and they range in size from 700m2 to 1,025m².

Stage 2A Civil Construction commenced in March 2024 and is ongoing.

Stage 2A was awarded to Lentro Earthworks in January 2024.

Stage 2A Subdivision Certificate was approved in May 2023.

Stage 2A DA modification was approved in March 2023.

Stage 2A DA was approved in September 2022.