Week 15 brings civil works up to the Christmas holiday break. Prior to week 15, works were ahead of schedule, however, progress has been slowed by wet weather, works are now approximately running on schedule with 90 percent of general earthworks completed.
Works onsite have included:
-
Monitoring of safety, environmental, erosion and quality controls;
-
95% of topsoil stripping completed;
-
90% of earthworks cut and fill completed;
-
10% of sewer trenching and pipe installation completed;
-
Stormwater trenching underway;
-
Demolition of house on entry road completed;
-
Sewer pump station construction certificate approval received from Yass Valley Council.