Week 19 progress report covers the first two weeks of works after a two week site shut down due to the Christmas holiday break. As of week 19 works completed onsite include:
-
Monitoring of safety, environmental, erosion and quality controls;
-
97% of topsoil stripping completed;
-
97% of earthworks cut and fill completed;
-
30% of sewer trenching, pipe installation and construction of sewer manholes completed;
-
10% Stormwater trenching underway;
-
Relocation of existing power lines through the site to enable continuation of earthworks.