Week 34 progress report is for work completed up to the end of April. Works completed up to Week 34 included:
-
Monitoring of safety, environmental, erosion and quality controls;
-
100% topsoil stripping completed;
-
100% earthworks cut and fill completed;
-
100% sewer trenching, pipe installation and construction of sewer manholes completed;
-
100% stormwater pipes layed and 100% stormwater pits installed;
-
100% sewer pump station components completed;
-
100% watermain works commenced and 80% of water services;
-
100% subsurface drains completed;
-
100% demolition of entry house and clearing works completed;
-
80% electrical high voltage, 60% low voltage, 45% street lights completed;
-
Road subbase construction commenced;
-
Sewer rising main installation commenced;
-
Removal of rail infrastructure, stripping in rail corridor and construction of ‘at grade’ crossing commenced;
-
NBN installation commenced;
-
Kerb & gutter commenced.