Week 19 progress report covers the first two weeks of works after a two week site shut down due to the Christmas holiday break. As of week 19 works completed onsite include:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 97% of topsoil stripping completed;

  • 97% of earthworks cut and fill completed;

  • 30% of sewer trenching, pipe installation and construction of sewer manholes completed;

  • 10% Stormwater trenching underway;

  • Relocation of existing power lines through the site to enable continuation of earthworks.