Week 65 progress report is for work completed up to mid-December. Works completed up to Week 65 included:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 100% topsoil stripping completed;

  • 100% earthworks cut and fill completed;

  • 100% sewer trenching, pipe installation and construction of sewer manholes completed;

  • 100% stormwater pipes layed and 100% stormwater pits installed;

  • 100% sewer pump station components completed;

  • 100% watermain works commenced and 100% of water services with connection still to occur;

  • 100% subsurface drains completed;

  • 100% demolition of entry house and clearing works completed;

  • 100% road subbase construction completed;

  • 100% kerb & gutter completed;

  • 100% NBN installation completed;

  • 100% sewer rising main installation completed;

  • 100% electrical works completed;

  • 100% topsoiling of lots and verges;

  • 100% final road wearing courses;

  • 100% retaining walls;

  • 95% footpaths completed;

  • 95% tree planting and general landscaping;

  • 80% Intersection, entry feature and entry landscaping.