Week 25 progress report is for works up until the end of February. A new up-to-date progress report is expected soon. Works completed up to Week 25 include:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 100% of topsoil stripping completed;

  • 99% of earthworks cut and fill completed;

  • 99% of sewer trenching, pipe installation and construction of sewer manholes completed;

  • 100% stormwater pipes layed and 50% stormwater pits installed;

  • Watermain works commenced;

  • Subsurface drains commenced;

  • Sewer pump station components completed;

  • Demolition of entry house completed, minor clearing works remaining.